Mona Bartsoff - FortisAlberta
OK, the utility owners have marked your site where you intend to dig if they have buried lines below using flags and paint. They have left you with a document as well called a Locate Slip. You are clear on how to dig safely and understand the responsibilities as a ground disturber. But, what if other things come up and you’re not actually ready to dig. How long do you have before needing refresh the request? What is the process?
Locates may be valid for up to 30 calendar days from the date they were provided subject to certain conditions being met. If a ground disturber has not started or completed a ground disturbance within the maximum timeframe of the existing locates or 30 calendar days from the date locates were requested, whichever is shorter, the ground disturber must request the locates be refreshed or re-done. Locates for a Large Project Ticket can be valid for up to 60 calendar days with the written concurrence of the affected owners/operators on the Locate Report.
Utility Safety Partners will re-notify individual member operators of buried facilities. They will reach out to you to determine whether a new locate is required or the lifespan of the existing locate can be extended. The length of this refreshed or extended lifespan will be determined by you and the buried facility operator together.
For large or long-term projects, it is expected that the ground disturber will break the project into sections when placing locate requests to better coordinate the provision of locates with the progress of the ground disturbance. If at any time you are of the opinion that the locate marks are not adequate for the successful and safe completion of the work, you must request new locates.
Always remember to follow safe digging processes. Learn more about Hand Expose Zones, Special Situations, Field Problems and other important ground disturbance practices by visiting The Damage Prevention Process in Alberta.