The TxDOT highway letting is scheduled for November 1st & 2nd. The total tonnage of hot mix being let is 882,654.
275 119,298 25 6,583 330 5,089 48,750 2,555 3,000 5 30 16,802 28,947 78,340 131 26,668 228,474 3,489 110,326 16,018 3,041 17,165 14,425 8,445 3,004 5,118 1,552 6,686 3,486 4,263 6,847 882,654
NUMBER
COUNTY
HWY
TYPE
TONS
1
ATASCOSA
CR
REPLACE BRIDGES AND APPROACHES
2
BASTROP
SH 71
CONSTRUCT OVERPASS, FRONTAGE ROADS AND RAMPS
3
BEXAR
IH 10
RETAINING WALL
4
BURLESON
SH 21
REHABILITATE EXISTING ROAD
5
CALHOUN
PW
REHABILITATE EXISTING ROADWAY
6
COLLINGSWORTH
US 83
REPLACE BRIDGE AND APPROACHES
7
DEAF SMITH
US 60
REHAB EXISTING ROADWAY EB LANES
8
EL PASO
IH 10
2" MILL AND INLAY ON VARIOUS ENTRANCE AND EXIT RAM
9
ELLIS
FM 985
BASE REPAIR
10
FORT BEND
US 59
GENERAL ROUTINE MAINTENANCE OF US 59
11
FORT BEND
SH 99
GUARDRAIL REPAIR
12
FREESTONE
IH 45
HMA OVERLAY
13
GRAYSON
FM 120
OVERLAY
14
HARRISON, ETC
IH 20, ETC
PLANE, CONC PVMT REP, ACP SF, PAV MRK
15
IRION
RM 853
CULVERT & LOW WATER CROSSING UPGRADE AND EXTENSION
16
JOHNSON
SH 171
PAVEMENT REPAIR AND OVERLAY
17
KENEDY
US 77
MILLING, ASPHALT PAVING, ETC.
18
LUBBOCK
US 62
INTERSECTION IMPROVEMENTS
19
MAVERICK
SH 131
BLADE LEVEL, OVERLAY, AND PVT EDGE REPAIR
20
MENARD
RM 864
ADDING BASE, CEMENT TREAT, SEAL COAT AND PAVEMENT
21
MONTGOMERY, ETC.
FM 2978
GR, STRS, BASE AND PAVE
22
NACOGDOCHES
FM 225
CONSTRUCT PAVED SHOULDERS AND OVERLAY
23
NACOGDOCHES
SH 204
PROVIDE ADDITIONAL PAVED SURFACE WIDTH
24
NUECES
FM 43
LEVEL UP
25
ORANGE
IH 10
REPLACE EXISTING BRIDGE AND APPROACHES
26
SAN PATRICIO
US 77
MILL AND OVERLAY
27
TRAVIS
US 183
ADD ENTRANCE RAMP
28
WALKER
US 190
OVERLAY
29
WEBB
IH 35
BLADE LEVEL UP, OVERLAY AND PAVEMENT EDGE REPAIR
113,487
30
WICHITA
SP 447
SPOT FULL DEPTH REPAIR AND OVERLAY
31
WILBARGER
BU 287F
OVERLAY
32
WILSON
SH 123
RESTORE EXISTING ROADWAY
TOTAL