The TxDOT highway letting is scheduled for July 9th and 10th. The total tonnage of asphalt pavements being let is 1,147,967.
# | COUNTY | HWY |
TYPE | TONS |
1 | ANGELINA | FM1194 | PROVIDE ADDITIONAL PAVED SURF WIDTH | 2,290 |
2 | ATASCOSA | IH37 | MILL,BS,SURF,SC,OV & PAV MRK (SBML) | 20,738 |
3 | BEXAR | IH35 | REFIG INTER, RMP, FRT & ML OP IMPRV | 81,794 |
4 | BOWIE | US59 | FLX BASE, SURF, CONC C&G,TS&PAV MKS | 312 |
5 | BRAZORIA | FM1462 | INTERSECTION IMPROVEMENTS | 2,475 |
6 | BRAZORIA | BS288B | RAISED MEDIAN | 498 |
7 | BRAZORIA | SH35 | ADD XOVER LT TN LN | 1,728 |
8 | BRAZOS | SH6 | UPGRADE EXISTING INTERCHANGE | 2,044 |
9 | CAMERON | US287 | REPLACE BRIDGE AND APPROACHES | 165 |
10 |
COLLIN | FM2514 | BS REP, OV | 6,694 |
11 |
COLORADO | FM102 | PAVEMENT REPAIR & SHOULDER WIDENING | 8,112 |
12 |
CORYELL | FM1113 | BASE REPAIR | 5,280 |
13 | DALLAS | SH121 | GRADING, STRUCTURES AND SURFACE | 94,597 |
14 | DALLAS | IH20 | FULL DEPTH REPAIR, MILL AND INLAY | 15,719 |
15 |
DALLAS | SH356 | REHABILITATE BRIDGE | 205 |
16 | DENTON | FM156 | ADD 10' SHOULDERS AND REHAB | 24,010 |
17 | DIMMIT | FM468 | OVERLAY, PAV MARKS | 4,124 |
18 | EASTLAND | IH20 | MILL & INLAY | 1,968 |
19 | EL PASO | LP375 | CONSTRUCT AUXILIARY LANES | 35,018 |
20 | EL PASO | CS | ROAD WIDENING | 3,818 |
21 |
ELLIS | FM879 | REPLACE BR & APPRS | 276 |
22 |
FT. BEND | CR | REPLACE BRIDGE AND APPROACHES | 43 |
23 |
FT. BEND | FM2234 | GR, STRS, BS & SURF | 4,433 |
24 |
FRIO | SH85 | PAVEMENT RESTORATION | 21,892 |
25 |
GONZALES | FM532 | ROADWAY WIDENING | 24,911 |
26 |
GRAYSON | FM902 | REHABILITATION OF EXISTING ROAD | 834 |
27 |
GREGG | SH42 | GR, STRS, SURF | 10,631 |
28 |
GRIMES | SH30 | CONSTRUCT PROTECTED LEFT-TURN LANE | 2,902 |
29 |
GRIMES | FM244 | ROADWAY RESTORATION | 1,375 |
30 |
GUADALUPE | IH10 | GRAD,BASE,STR,SURF,PAV'T MRK,SIGNS | 15,497 |
31 |
HAMILTON | PW | EXTEND/CONSTR ACCESS RD/PARKING FAC | 411 |
32 |
HARRIS | FM2920 | INTERSECTION IMPROVEMENTS | 18,057 |
33 | HARRIS | FM1093 | IMPLEMENTATION OF ACCESS MGMT | 51 |
34 |
HARRIS | CS | REPLACE BRIDGE AND APPROACHES | 203 |
35 |
HARRIS | US59 | ASPHALT O/L W/ PV MKS | 66,869 |
36 | HAYS | SH123 | ADD LEFT TURN LANE | 1,824 |
37 |
HAYS | SH21 | CONSTR LEFT TURN LANE ON SH 21 NB | 1,812 |
38 | HIDALGO | FM3461 | CONST 4 LN DIV URB | 6,653 |
39 | HIDALGO | US83 | INTERCHANGE IMPROVEMENTS | 42,476 |
40 | HILL | FM934 | BASE REPAIR | 427 |
41 | HOOD | US377 | FLEXIBLE PAVEMENT STRUCTURE REPAIR | 2,000 |
42 | HOWARD | US87 | SPOT REPAIR / SEAL / OVERLAY | 10,642 |
43 | JEFFERSON | US87 | REPLACE BRIDGE AND APPROACHES | 1,280 |
44 | JEFFERSON | US69 | REPLACE BRIDGE AND APPROACHES | 921 |
45 | JEFFERSON | US69 | GR, BS, PVMT, STR | 61,112 |
46 | JOHNSON | US67 | GRADING, STRUCTURES, BASE, & SURF | 32,022 |
47 | LAMAR | FM137 | REHABILITATION OF EXISTING ROAD | 2,285 |
48 | LEON | US79 | CONSTRUCT PROTECTED LEFT-TURN LANE | 2,383 |
49 | LEON | US79 | REHABILITATE EXISTING ROAD | 16,737 |
50 | LIMESTONE | FM339 | BASE REPAIR | 807 |
51 | LUBBOCK | US87 | CONSTRUCTION OF GRADE SEPARATION | 29,636 |
52 | MADISON | FM3091 | ROADWAY RESTORATION | 76 |
53 | McLENNAN | IH35 | WDN, GR & STRS | 14,962 |
54 | McLENNAN | FM933 | BASE REPAIR | 6,339 |
55 | MEDINA | IH35 | GRAD, BSE, SURF, PAVMNT MRK, SIGNS | 2,362 |
56 | MILLS | US84 | HOT MIX OVERLAY | 7,291 |
57 | MONTGOMERY | FM1488 | CONSTRUCT RR GRADE SEPARATION | 11,825 |
58 | MONTGOMERY | FM3083 | WIDEN ROADWAY | 22,049 |
59 | MONTGOMERY | CR | CONST 2 LANE RDWY | 1,861 |
60 | MORRIS | CR | REPLACE BRIDGE AND APPROACHES | 207 |
61 | NUECES | US77 | MILL & INLAY | 2,758 |
62 | NUECES | US77 | GRADE,BASE,SURF,STRS | 82,725 |
63 | ORANGE | BU90Y | REPAIR BRIDGE SUBSTRUCTURE | 4 |
64 | ORANGE | IH10 | GR, BS, PVMT & STR | 88,206 |
65 | ROBERTSON | US79 | CONSTRUCT PROTECTED LEFT-TURN LANE | 3,615 |
66 | ROCKWALL | IH30 | STR,GRD,BASE,CONC PVMT,SIGNS,MRKS | 34,056 |
67 | RUSK | SH64 | GR,STRS,PLNG,HMA BS,C&G,SURF,PV MKG | 2,634 |
68 | SHELBY | US84 | REPLACE BRIDGE | 15,207 |
69 | STEPHENS | US180 | MILL & INLAY (WILL-CALL AS NEEDED) | 1,739 |
70 | TARRANT | SH114 | GR, BS, STRUCT AND PAVEMENT | 594 |
71 | TARRANT | VA | BRIDGE REPAIR | 7,412 |
72 | TOM GREEN | FM388 | WIDEN AND RESURFACE | 6,395 |
73 | TRAVIS | LP212 | PAVEMENT REPAIR,MILL,SEAL&OVERLAY | 2,040 |
74 | UPSHUR | US271 | INSTALL LEFT TURN LANES | 8,585 |
75 | UPSHUR | SH155 | REPLACE BRIDGES AND APPROACHES | 402 |
76 | UVALDE | SH55 | RECONSTRUCT RDWY DRNGE & OP IMRPROV | 4,244 |
77 | VICTORIA | US59 | REPLACE BRIDGES AND APPROACHES | 7,219 |
78 | WALLER | CR | REPLACE BRIDGE | 435 |
79 | WASHINGTON | SH36 | REHABILITATE EXISTING ROAD | 13,582 |
80 | WASHINGTON | SH105 | CONSTRUCT PROTECTED LEFT-TURN LANE | 702 |
81 | WHARTON | SH71 | ACP OVERLAY | 8,502 |
82 | WICHITA | US82 | OVERLAY | 13,934 |
83 | WILLACY | CR | REPLACE BRIDGE & RECONST APPROACHES | 374 |
84 | WILLIAMSON | FM112 | REPLACE BRIDGE & APPROACHES | 1,033 |
85 | ZAPATA | US83 | REHAB & WIDEN PAVEMENT (SUPER 2) | 20,495 |
TOTALS SCHEDULED FOR JULY | 1,147,967 |